Task
estimate calculator
A single guess is usually wrong. Give a best case, a most likely and a worst case, and get one expected time that weighs them sensibly.
- About 1 minute
- Free, no sign-up
- Standard method, sources below
Expected time
5.5 days
Weighted towards your most likely estimate. A simple average of the three would be 6 days.
- Spread (standard deviation)
- 1.17 days
- Simple average
- 6 days
An estimate, not a promise. The spread is a rough guide, people tend to set best and worst cases too close together, and adding up estimates for tasks that run side by side understates the risk.
How we worked it out
A three-point (PERT) estimate gives the most likely estimate four times the weight of the best and worst cases.
- 1Expected time(3 + 4 × 5 + 10) ÷ 65.5 days
- 2Spread(10 − 3) ÷ 61.17 days
Questions people ask
Why weight the most likely estimate four times?
That's the standard three-point (PERT) formula: (best + 4 × likely + worst) ÷ 6. It leans on your most likely estimate while still allowing for things going well or badly.
How accurate is it?
It's a rough guide. People tend to set best and worst cases too close together, and adding up estimates for tasks that run side by side understates the risk.
Sources
Checked 10 Nov 2026. These are published methods, not law.
- Project Management Institute: Practice Standard for Scheduling (2nd edition)(opens in a new tab)The three-point (PERT) estimate, and its limits.
- NASA: Program Risk Analysis Handbook (TM-100311)(opens in a new tab)PERT and triangular estimates, and why ranges are often too narrow.
- Brunel University (J E Beasley): OR-Notes, PERT(opens in a new tab)The spread: (worst − best) ÷ 6.
Spend less time in meetings
BizEdge Tasks & Projects lets you assign tasks, set deadlines and see progress across your team, without calling a meeting to find out.
- 1Create your free BizEdge account
- 2Add your team
- 3Set up your first project